Import Protected Days and Holidays

Import an ".ics" file into LightDesigner including the holidays and special events you require for your project. An *.ics calendar file is a standard filename extension used to designate a file containing calendar and schedule information. Some programs that utilize the .ics file format include Apple Inc.'s iCal® application program, Google Calendar™, and Microsoft® Outlook 365™.

Note: Importing holidays (.ics calendar file) into LightDesigner does not apply any default actions to them, it simply adds events with a defined date range for later assignment.

LightDesigner provides two methods to import protected days and holidays including the action in the Project menu and the tool located in the toolbar of the Timed Events view. See also Protected Days and Holidays for more specific information about using these features.

Import from the Project menu

  1. Select Project > Import Data > Protected Days and Holidays. The "Import Protected Days and Holidays" window displays.
  2. Browse to the directory that includes the *.ics file with the specific protected days and/or holidays for import.
  3. Click [Open]. All holidays in the imported calendar will populate into the Holidays and Protected Days lists in the current project or server project open in LightDesigner.

Import from the Timed Events view

  1. From the Timed Events View, select the "Protected Days and Holidays" icon located in the toolbar. The "Import Protected Days and Holidays" window displays for file selection.
  2. Browse to the file location and select the *.ics file that includes the protected days and/or holidays for import.
  3. Press [Open]. All holidays in the imported calendar will populate into the Holidays listing in LightDesigner.